LINCOLN COUNTY NOTICE OF APPLICATION AND DETERMINATION OF NON-SIGNIFICANCE

LINCOLN COUNTY NOTICE

OF APPLICATION AND DETERMINATION

OF NON-SIGNIFICANCE

(DNS) STATE

ENVIRONMENTAL POLICY

ACT (SEPA) (RCW 43.21C)

SEPA RULES (WAC 197-11)

AND NOTICE OF PUBLIC

HEARING

FILE NO. Conditional Use Permit

– 01-23

DESCRIPTION OF PROPOSAL:

Expand the existing Wilbur

pit by 36.7 acres for a total of

96.2 acres and continue development

of the existing surface

mine. The site would also be

used for stockpiling crushed

products and a temporary asphalt

or concrete batch plant to

produce products.

PROPONENT:

Copenhaver Construction, Inc

22393 SR 2 E

Creston, WA 99117

LOCATION OF PROPOSAL:

NW ¼ & SW ¼ of section 12,

township 26N, range 32 EWM.

LEAD AGENCY: Lincoln County

Land Services

DETERMINATION: The lead

agency for this proposal has

determined that it does not

have a probable significant

adverse impact of the environment.

An environmental impact

statement (EIS) is not required

under RCW 43.21C.030. This

decision was made after review

of a completed environmental

checklist and other information

on file with the lead agency.

This information is available to

the public on request. This DNS

is issued under 197-11- 340(2)

and the lead agency will not act

on this proposal for 14 days from

the date below. Comments must

be submitted by 3:30 PM May

18, 2023.

This Determination of Non-Significance

is issued pursuant to

the applicant’s compliance with

the following:

1. Compliance with applicable

Lincoln County building, zoning,

development, county road ingress/

egress requirements and

all state/federal requirements.

Mailing & Street Address: Lincoln

County Land Services,

27234 SR 25 N, Davenport,

WA, 99122.

Phone (509) 348-0130

Date: May 4, 2023

Responsible Official: Courtney

Thompson, Planner

Signature Courtney Thompson

Date: 05/4/2023

APPEALS: You may appeal this

SEPA threshold determination

in writing to the responsible

official listed above no later than

May 29, 2023. You should be

prepared to make specific factual

objections.

PUBLIC HEARING: A public

hearing on the application

for a Conditional Use Permit

is scheduled before the Lincoln

County Hearing Examiner

on Wednesday May 24th at

2:00 PM in the Commissioners

Chambers (basement of courthouse)-

450 Logan St Davenport,

WA 99122. This meeting

will also be available via zoom,

visit https://www.co.lincoln.

wa.us/land-services/planning/

for meeting information.

Published May 4 and 11, 2023

 